In Naka City, Ibaraki Prefecture, Japan’s JT-60SA is running again.

On 27 February 2026, the National Institutes for Quantum Science and Technology (QST) started integrated commissioning of the upgraded tokamak. QST and Europe’s Fusion for Energy (F4E) announced the restart on 13 March.

A few months later, on 27 August, the Korea Institute of Fusion Energy (KFE) said it had signed a project plan with four European fusion laboratories to study long discharges in KSTAR once the machine’s plasma-facing surfaces are converted to tungsten.

These are two of the biggest public fusion machines in Japan and South Korea now moving through major experimental programmes. Both are tokamaks, devices that use magnetic fields to hold extremely hot plasma in place. If fusion electricity is ever demonstrated, it will rest on that kind of operating knowledge: how to heat, control and sustain plasma while managing the materials and systems around it. In Asia-Pacific, Japan and South Korea are among the few places running large machines that do that work in public view, and in partnership with Europe, while ITER is still under construction in France.

The engineering work in 2026 is about learning how to heat and control plasma, manage the materials facing it, and keep the machine operating for longer periods. JT-60SA is working towards heated plasma on an upgraded machine designed to support ITER and research towards DEMO. KSTAR is preparing to operate long-pulse plasma against tungsten surfaces alongside European laboratories that already work with the material.

JT-60SA is learning how to heat and hold a plasma

QST describes JT-60SA as a superconducting tokamak and the largest operating tokamak until ITER in France comes online. Its role spans three areas: supporting ITER’s technical goals, conducting complementary research towards DEMO, and developing the people needed to operate future fusion facilities.

DEMO is the proposed demonstration plant that would follow ITER and seek to show that fusion can generate electricity. JT-60SA therefore sits upstream of the demonstration plant, testing operating approaches before they are needed at that scale.

Integrated commissioning is the first part of that process. It is the gradual verification that the machine works as a complete system, from vacuum pumping and cooling the superconducting coils to energising the magnets and eventually producing and controlling plasma.

The restart follows a roughly two-year pause after low-power plasma operations in late 2023. The upgrade includes European diagnostics and cryopumps, additional heating systems, a new carbon-based first wall and divertor, and Japanese-installed in-vessel control coils. QST describes the new coils as a world-first experience for a large superconducting tokamak, including two ring coils about eight metres across designed to provide fast control of plasma position.

The next major milestone is plasma heating.

QST says heating experiments are planned within 2026, while F4E says a new round of experiments is expected to begin towards the end of the year and run for around six months. That would put part of the campaign into early 2027 if the current target holds.

As of the March announcements, neither organisation had reported a delay. But there was also no mid-year public status that would justify treating the end-2026 start as certain.

ITER will eventually operate with much more energetic, reactor-relevant plasmas. JT-60SA gives researchers and engineers another large superconducting machine on which to develop experience with plasma heating and control before ITER reaches that stage.

Its current carbon-armoured configuration is also part of the learning path. That makes JT-60SA's materials story different from what KSTAR is preparing for.

KSTAR is building a tungsten long-pulse classroom

KSTAR’s August announcement addresses a related but different problem.

KFE signed what it calls the Project Plan for Joint Investigation of Long Discharges in KSTAR in a Tungsten Environment with four European fusion laboratories: CEA Cadarache in France, ENEA’s Frascati Research Centre in Italy, the Max Planck Institute for Plasma Physics in Germany and VTT Technical Research Centre of Finland. All are part of the EUROfusion consortium.

The division of work is clear. KSTAR brings experience in long-pulse, high-performance plasma operation. The European partners bring experience with tungsten devices, including WEST at CEA and ASDEX Upgrade at IPP. The programme combines experiments on KSTAR with shared data analysis and modelling.

Tungsten is central to the collaboration.

Future fusion reactors are expected to use tungsten for plasma-facing components because of its ability to withstand extreme heat and particle loads. But putting tungsten close to a plasma creates its own problems. Material can enter the plasma as an impurity, while the internal components have to absorb enormous heat loads.

KFE identifies several of the resulting challenges: impurity control, heat-load reduction, plasma-instability control, disruption mitigation and diagnostics for tungsten components.

The aim is to test long-pulse operating technologies in an environment closer to that expected in a future fusion reactor, while also establishing KSTAR as an international research platform.

The hardware change comes first. KFE has scheduled the replacement of plasma-facing internal components with tungsten for the second half of 2026. That upgrade is the precondition for the long-pulse programme described in the August plan.

The English-language KFE announcement does not publish the full signed instrument’s duration or a detailed experiment calendar. Secondary reports have supplied additional timelines, including five-year language and a concentration of activity across 2026 and 2027. Those details are better treated cautiously until the underlying Project Plan is publicly available.

KSTAR already has experience with tungsten. KFE records the completion of a tungsten divertor in 2023 and long-pulse results in a tungsten environment in 2024, including an ultra-high-temperature plasma of about 48 seconds and H-mode operation of about 102 seconds.

The new programme extends that work.

Put alongside JT-60SA, the complementarity is practical. Japan is commissioning a large superconducting machine towards heated-plasma experiments on a carbon-armoured upgrade path tied closely to ITER. South Korea is preparing KSTAR for long-pulse operation with tungsten, working with European laboratories that already have experience operating with the material.

Same stage of fusion development, different experimental jobs.

The alliance layer is part of the machine

The international structure behind these programmes matters because fusion research increasingly depends on specialised machines sharing knowledge, components, researchers and operating experience.

JT-60SA sits within the Broader Approach agreement between Euratom and Japan, signed in 2007. The partnership covers three Japan-hosted projects: JT-60SA in Naka, IFMIF/EVEDA and IFERC in Rokkasho.

QST is the Japanese implementing agency for JT-60SA and F4E is the European one. The programme is overseen through a Broader Approach Steering Committee with equal Japan-EU representation.

That makes the joint QST-F4E announcement more than a routine project update. It is an update from a shared piece of scientific infrastructure.

KSTAR’s August programme is different. It is a KFE–EUROfusion collaboration outside the Broader Approach framework, but the institutional logic is similar. Capability is distributed across machines and countries, with researchers bringing operating experience from one facility to another.

F4E’s March note said the JT-60SA experiment team was already reviewing more than 150 proposals, with EUROfusion laboratories and the ITER Organization expected to participate from Naka.

That is what an experimental testbed looks like in practice: different machines, laboratories and researchers tackling different parts of the same engineering problem.

How to read the next fusion headline

Fusion news often arrives as a countdown to grid power. The operator language from JT-60SA and KSTAR is quieter, and it is a clearer guide to where the technology sits.

QST and F4E are talking about integrated commissioning, plasma heating, ITER support, DEMO-oriented research and human-resource development. KFE is talking about long-pulse operation in a tungsten environment and the technologies needed for future reactor operation. These are R&D and operations milestones. The public announcements give no commercial power output target or go-live date.

For Japan and South Korea in 2026, these tokamaks are experimental infrastructure. The near-term work is heating campaigns, plasma control, wall materials, impurity management, disruption mitigation and the people learning how to operate the machines. The alliance story is who brings the expertise, equipment and researchers into that work.

The knowledge being built in Naka and on KSTAR is meant to travel towards DEMO and, over a longer horizon, into the industrial, research and talent networks that will support fusion beyond these machines. That is a distant energy prospect, not a near-term power story. For now, Japan and South Korea are places where the operating expertise for that future is being built.

What to watch

JT-60SA: Whether QST and F4E continue to describe plasma heating experiments as a 2026 or end-2026 milestone as the year closes, or whether the public timeline moves.

KSTAR: Whether the second-half 2026 tungsten plasma-facing upgrade completes on schedule, and when the first joint long-pulse experiments with CEA, ENEA, IPP and VTT are publicly described.

The alliances: Whether Broader Approach and KFE–EUROfusion staffing, proposals and joint experiments remain visible measures of research depth alongside commercial fusion timelines that describe a different stage of the technology.